Utility Master Plans

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

On September 21, 2006, the City authorized Carollo Engineers, P.C. (Carollo) to prepare
these water, sewer, storm drain system master plan studies, which included the following tasks:

• Establish systems planning and evaluation criteria.
• Review existing system deficiencies and propose improvements to enhance system capacity.
• Recommend improvements needed to service anticipated future growth.
• Develop a Capital Improvement Program (CIP) with a planning horizon of 2030.

Water system master plan

• Evaluate the existing water distribution system.
• Perform a demand analysis and review supply capacity.
• Perform a system-wide storage analysis. 

Sewer system master plan

• Create and calibrate a hydraulic computer model of the collection system.
• Evaluate the capacity of the existing sewer collection system. 

Storm Drain system master plan

• Create a hydraulic and hydrologic computer model of the storm drainage system.
• Evaluate the capacity of the existing storm drainage system.